1. Date of Order : 23.03.07
2. Time of commercial operation: 33 months
3. Progress of Work:
A. Boiler Foundations : Complete
B. Boiler Erection:
i) Non-pressure Parts : 1620 MT achieved (scope-3920 MT)
ii) Pressure Parts : 227 MT achieved (scope-2953MT)
C. Boiler Auxiliaries : ID Fan-B Foundation casting in progress.
ID Fan-A Excavation completed.
D. Power House
i) Civil work : All Main Column foundations complete.
Aux Column foundations in progress (70% achieved).
CW Pit Wall complete and CEP Foundation in progress.
3no BFP foundations complete and Oil Cooler Pits in prog.
TG Foundation in progress upto EL (+) 10.4M (Spring bot).
(Revised Target for TG Top Deck casting – 17.01.09).
ii) Structural work : Scope-4500 MT. Released – 3800MT. Fabrication
Achieved- 2015MT. Erected -440MT.
iii) Constraints : Resource crisis for Structural work.
E. ESP : Civil – 40 no Pedestals completed out of total 120 no. (Work Progress on A & B passes almost nil).
F. ESP Control Room : Completed upto EL+4.0M Floor soffit.
(Shuttering/Rebar work for +4.0M Floor taken up)
G. Chimney : Shell casting achieved-EL+92M.
H. Cooling Tower : Basin raft cast for Three Cells (total 13no).
Wall casting in progress. Excavation for balance Cells done.
(Constraints : Delay in additional PCC Filling by BHEL/GDC + Manpower crisis of PCT + Super-structure drawings yet to be released by PEM ).
I. CW Pump house : i)Civil work in progress for CW Duct only.
(30 RM of Raft cast).
ii) Excavation for Feedpool in progress.
(Constraints : Adequate Manpower mobilization required by GDC
for CWPH & Feedpool civil work).
J. Mill Bunker : Drawings are available. Work not started for Front not available (for Boiler Erection work).
K. CW Pipe Laying : Order for Execution Agency not placed yet.
L. Ash Handling System : Order Placed on M/s. DCIPS. Site Mobilisation pending.
M. 220kV Switchyard : Civil drawings available. Vendor not finalized.
2. Time of commercial operation: 33 months
3. Progress of Work:
A. Boiler Foundations : Complete
B. Boiler Erection:
i) Non-pressure Parts : 1620 MT achieved (scope-3920 MT)
ii) Pressure Parts : 227 MT achieved (scope-2953MT)
C. Boiler Auxiliaries : ID Fan-B Foundation casting in progress.
ID Fan-A Excavation completed.
D. Power House
i) Civil work : All Main Column foundations complete.
Aux Column foundations in progress (70% achieved).
CW Pit Wall complete and CEP Foundation in progress.
3no BFP foundations complete and Oil Cooler Pits in prog.
TG Foundation in progress upto EL (+) 10.4M (Spring bot).
(Revised Target for TG Top Deck casting – 17.01.09).
ii) Structural work : Scope-4500 MT. Released – 3800MT. Fabrication
Achieved- 2015MT. Erected -440MT.
iii) Constraints : Resource crisis for Structural work.
E. ESP : Civil – 40 no Pedestals completed out of total 120 no. (Work Progress on A & B passes almost nil).
F. ESP Control Room : Completed upto EL+4.0M Floor soffit.
(Shuttering/Rebar work for +4.0M Floor taken up)
G. Chimney : Shell casting achieved-EL+92M.
H. Cooling Tower : Basin raft cast for Three Cells (total 13no).
Wall casting in progress. Excavation for balance Cells done.
(Constraints : Delay in additional PCC Filling by BHEL/GDC + Manpower crisis of PCT + Super-structure drawings yet to be released by PEM ).
I. CW Pump house : i)Civil work in progress for CW Duct only.
(30 RM of Raft cast).
ii) Excavation for Feedpool in progress.
(Constraints : Adequate Manpower mobilization required by GDC
for CWPH & Feedpool civil work).
J. Mill Bunker : Drawings are available. Work not started for Front not available (for Boiler Erection work).
K. CW Pipe Laying : Order for Execution Agency not placed yet.
L. Ash Handling System : Order Placed on M/s. DCIPS. Site Mobilisation pending.
M. 220kV Switchyard : Civil drawings available. Vendor not finalized.
25th June 2013, 13:34 by rajena
» Progress Report of Unit No. 6 for the month of May 2009
19th June 2009, 14:15 by mbdcl
» Progress/Program of M/s. BHEL for Major Balance Activities.
27th April 2009, 14:35 by mbdcl
» Unit No.5 : Status of Pending BOP work.
27th April 2009, 14:15 by mbdcl
» Unit No.5 : Status of Pending BOP work.
27th April 2009, 14:14 by mbdcl
» Updated Status of Balance work on Main Plant package
13th March 2009, 18:00 by mbdcl
» Updated Status of Unit-5 Balance Work for BOP Package
12th March 2009, 19:12 by mbdcl
» Status Report of Unit No.6 Construction as on 12.03.09.
12th March 2009, 14:48 by mbdcl
» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
9th February 2009, 18:03 by mbdcl