1. Date of Order : 23.03.07
2. Time of commercial operation: 33 months
3. Progress of Work:
A. Boiler Foundations : Complete
B. Auxiliaries : ID Fan- A & B foundation complete.
Duct Support Foundations (ESP to ID Fan) complete.PA & FD Fan foundations not started to facilitate Boiler erection.
C. Boiler Erection:
i) Non-pressure Parts : 2115 MT achieved (scope-3920 MT)
ii) Pressure Parts : 1350 MT achieved (scope-2593 MT)
D. ESP : Total achieved 835 MT out of 4072 MT).
E. Power House Bldg
i) Civil work : Major Foundations including TG complete.
Operating Floors : Work is in slow progress at +8.5M & +13.5M in A-B & B-C bays and also at +3.5M & 10M in C-D bay for i) delay in structural readiness, ii) Manpower shortage.
Total achieved 450 Cum out of 2000 Cum.
ii) Structural work : Scope-4700 MT. Released – 4700MT.
Fabrication Achieved- 4400MT. Erected - 4000MT.
(In details : All Main Columns are erected, 9no Roof Truss erected in TG Hall portion out of 10no,
16no Crane Girders erected out of 20no and erection/welding/torque tightening of Floor Beams is in slow progress at various levels).
F. ESP Control Room : Floors at EL+4.0M, +9.0M, EL+13M & +17M cast. Ground Floor cast. Brickwork is in progress.
G. Chimney (220m Ht) : Shell casting completed on 21.03.09. Inside Corbels casting
completed upto EL +65M.
H. Cooling Tower : Basin Floor raft cast for all 13 Cells.
Civil work for Super-structure completed till 5th level for six (6) Cells. For balance 7 Cells, civil work in progress till 1st level. (2690 cum concrete poured against scope of total 6000 cum.)
I. CW Pump house : Sump Base Raft complete. Casting of Wall/Columns is in
& Feed Pool under progress till bottom of Operating Floor EL-3.5M
CW Duct : Major Civil work achieved.
J. Clf Wat Reservoirs : Base raft (in two tiers) casting is in progress. Sand filling is & Pump House in progress.
K. Mill Bunker : Foundations completed for 50% area as front available.
Fabrication in progress for Columns/Bunker girders (achieved 750 MT out of 2700MT).
(Work Front for balance foundations not available).
L. CW Pipe Laying : Excavation & Pipe laying is under progress (Appx 374 RM of Pipe laid out of 1110 RM).
M. Transformer Yard : Foundations for Gen Transformer is under progress.
Excavation is under progress for Station Transformer.
N. 220kV Switchyard : Work front available only for 4no Tower Foundations. Civil work is under slow progress.
O. Ash Handling System :Order Placed on M/s. DCIPS. Work not started yet. Drawings are not available. Time of completion–22 months.
(Very Critical).
P. Erection of TG & Aux: Vendor Ordering not finalised.
2. Time of commercial operation: 33 months
3. Progress of Work:
A. Boiler Foundations : Complete
B. Auxiliaries : ID Fan- A & B foundation complete.
Duct Support Foundations (ESP to ID Fan) complete.PA & FD Fan foundations not started to facilitate Boiler erection.
C. Boiler Erection:
i) Non-pressure Parts : 2115 MT achieved (scope-3920 MT)
ii) Pressure Parts : 1350 MT achieved (scope-2593 MT)
D. ESP : Total achieved 835 MT out of 4072 MT).
E. Power House Bldg
i) Civil work : Major Foundations including TG complete.
Operating Floors : Work is in slow progress at +8.5M & +13.5M in A-B & B-C bays and also at +3.5M & 10M in C-D bay for i) delay in structural readiness, ii) Manpower shortage.
Total achieved 450 Cum out of 2000 Cum.
ii) Structural work : Scope-4700 MT. Released – 4700MT.
Fabrication Achieved- 4400MT. Erected - 4000MT.
(In details : All Main Columns are erected, 9no Roof Truss erected in TG Hall portion out of 10no,
16no Crane Girders erected out of 20no and erection/welding/torque tightening of Floor Beams is in slow progress at various levels).
F. ESP Control Room : Floors at EL+4.0M, +9.0M, EL+13M & +17M cast. Ground Floor cast. Brickwork is in progress.
G. Chimney (220m Ht) : Shell casting completed on 21.03.09. Inside Corbels casting
completed upto EL +65M.
H. Cooling Tower : Basin Floor raft cast for all 13 Cells.
Civil work for Super-structure completed till 5th level for six (6) Cells. For balance 7 Cells, civil work in progress till 1st level. (2690 cum concrete poured against scope of total 6000 cum.)
I. CW Pump house : Sump Base Raft complete. Casting of Wall/Columns is in
& Feed Pool under progress till bottom of Operating Floor EL-3.5M
CW Duct : Major Civil work achieved.
J. Clf Wat Reservoirs : Base raft (in two tiers) casting is in progress. Sand filling is & Pump House in progress.
K. Mill Bunker : Foundations completed for 50% area as front available.
Fabrication in progress for Columns/Bunker girders (achieved 750 MT out of 2700MT).
(Work Front for balance foundations not available).
L. CW Pipe Laying : Excavation & Pipe laying is under progress (Appx 374 RM of Pipe laid out of 1110 RM).
M. Transformer Yard : Foundations for Gen Transformer is under progress.
Excavation is under progress for Station Transformer.
N. 220kV Switchyard : Work front available only for 4no Tower Foundations. Civil work is under slow progress.
O. Ash Handling System :Order Placed on M/s. DCIPS. Work not started yet. Drawings are not available. Time of completion–22 months.
(Very Critical).
P. Erection of TG & Aux: Vendor Ordering not finalised.
25th June 2013, 13:34 by rajena
» Progress Report of Unit No. 6 for the month of May 2009
19th June 2009, 14:15 by mbdcl
» Progress/Program of M/s. BHEL for Major Balance Activities.
27th April 2009, 14:35 by mbdcl
» Unit No.5 : Status of Pending BOP work.
27th April 2009, 14:15 by mbdcl
» Unit No.5 : Status of Pending BOP work.
27th April 2009, 14:14 by mbdcl
» Updated Status of Balance work on Main Plant package
13th March 2009, 18:00 by mbdcl
» Updated Status of Unit-5 Balance Work for BOP Package
12th March 2009, 19:12 by mbdcl
» Status Report of Unit No.6 Construction as on 12.03.09.
12th March 2009, 14:48 by mbdcl
» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
9th February 2009, 18:03 by mbdcl