Sl No | Major Milestones | Original Targets as per L1 | Fresh Targets of M/s. BHEL |
1 | Boiler Drum Lifting | 13.04.08 | 02.10.08 (Done) |
2 | Start of TG & Condenser Erection | 24.06.08 | 17.01.09 |
3 | Boiler Hydro Test | 27.12.08 | 24.04.09 |
4 | Turbine & Generator Box-up | 26.01.09 | 30.06.09 |
5 | Turbine On Barring Gear | 20.04.09 | 25.08.09 |
6 | Boiler Light Up | 29.05.09 | 30.08.09 |
7 | Synchronization | 20.07.09 | 30.11.09 |
8 | Coal Firing & Continuous Operation of Unit | 08.09.09 | 29.12.09 |
9 | Trial Operation Completion | 09.09.09 | 28.01.10 |
Search
Latest topics
STPS Extension Unit No.6 (1 x 250MW) Major Milestones Committed by M/s. BHEL
sukantasenroy- Posts : 7
Join date : 2008-08-31
|
|
25th June 2013, 13:34 by rajena
» Progress Report of Unit No. 6 for the month of May 2009
19th June 2009, 14:15 by mbdcl
» Progress/Program of M/s. BHEL for Major Balance Activities.
27th April 2009, 14:35 by mbdcl
» Unit No.5 : Status of Pending BOP work.
27th April 2009, 14:15 by mbdcl
» Unit No.5 : Status of Pending BOP work.
27th April 2009, 14:14 by mbdcl
» Updated Status of Balance work on Main Plant package
13th March 2009, 18:00 by mbdcl
» Updated Status of Unit-5 Balance Work for BOP Package
12th March 2009, 19:12 by mbdcl
» Status Report of Unit No.6 Construction as on 12.03.09.
12th March 2009, 14:48 by mbdcl
» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
9th February 2009, 18:03 by mbdcl