Santaldih Thermal Power Station - WBPDCL

Would you like to react to this message? Create an account in a few clicks or log in to continue.
Santaldih Thermal Power Station - WBPDCL

This site is made for sharing information of STPS & on going projects at STPS - Unit#5 and Unit#6

Latest topics

» santhaldih tps web site
STATUS OF 6th Unit MECHANICAL WORK on 18/11/2008 Empty25th June 2013, 13:34 by rajena

» Progress Report of Unit No. 6 for the month of May 2009
STATUS OF 6th Unit MECHANICAL WORK on 18/11/2008 Empty19th June 2009, 14:15 by mbdcl

» Progress/Program of M/s. BHEL for Major Balance Activities.
STATUS OF 6th Unit MECHANICAL WORK on 18/11/2008 Empty27th April 2009, 14:35 by mbdcl

» Unit No.5 : Status of Pending BOP work.
STATUS OF 6th Unit MECHANICAL WORK on 18/11/2008 Empty27th April 2009, 14:15 by mbdcl

» Unit No.5 : Status of Pending BOP work.
STATUS OF 6th Unit MECHANICAL WORK on 18/11/2008 Empty27th April 2009, 14:14 by mbdcl

» Updated Status of Balance work on Main Plant package
STATUS OF 6th Unit MECHANICAL WORK on 18/11/2008 Empty13th March 2009, 18:00 by mbdcl

» Updated Status of Unit-5 Balance Work for BOP Package
STATUS OF 6th Unit MECHANICAL WORK on 18/11/2008 Empty12th March 2009, 19:12 by mbdcl

» Status Report of Unit No.6 Construction as on 12.03.09.
STATUS OF 6th Unit MECHANICAL WORK on 18/11/2008 Empty12th March 2009, 14:48 by mbdcl

» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
STATUS OF 6th Unit MECHANICAL WORK on 18/11/2008 Empty9th February 2009, 18:03 by mbdcl


    STATUS OF 6th Unit MECHANICAL WORK on 18/11/2008

    avatar
    sukantasenroy


    Posts : 7
    Join date : 2008-08-31

    STATUS OF 6th Unit MECHANICAL WORK on 18/11/2008 Empty STATUS OF 6th Unit MECHANICAL WORK on 18/11/2008

    Post  sukantasenroy 19th November 2008, 14:15

    BOILER


    25th April’08 is zero date of 6th unit, STPS (1x250 MW). KPEL is the subcontractor, who is taking care the Boiler Erection.Total non pressure parts erection quantity is 1543.16 MT including alignment, bolting & welding support and pressure parts erection quantity is 205.71 MT so far.


    Out of 30 columns so far 23 has been erected along with 5 girders. Boiler drum has been lifted on 2nd oct. 2008.
    Boiler main column =13/13
    Auxiliary column =10/11
    Air pre-heater main column=0/6
    Four I BR welder selected in presence of boiler inspector for pressure parts.

    Pressure welding completed so far
    Joints are as follows:
    TOTAL NO.S of LTSH joint : 198/682
    Down comer:

    NO. OF JOINT: 6/56

    Details:
    DC-2J2; DC-5J2 ; DC-6J4 & DC-1J4
    DC-4J2;


    Header lifted:

    TURBINE


    Column erection is going on

    ESP


    Mechanical work is yet to start as civil foundation work is under progress.

    Condensate storage tank (500 kl)

    5th units as well as 6th unit CS tank are ready.

      Current date/time is 17th May 2024, 17:36