Santaldih Thermal Power Station - WBPDCL

Would you like to react to this message? Create an account in a few clicks or log in to continue.
Santaldih Thermal Power Station - WBPDCL

This site is made for sharing information of STPS & on going projects at STPS - Unit#5 and Unit#6

Latest topics

» santhaldih tps web site
Status Report of Unit No.6 Construction as on 12.03.09. Empty25th June 2013, 13:34 by rajena

» Progress Report of Unit No. 6 for the month of May 2009
Status Report of Unit No.6 Construction as on 12.03.09. Empty19th June 2009, 14:15 by mbdcl

» Progress/Program of M/s. BHEL for Major Balance Activities.
Status Report of Unit No.6 Construction as on 12.03.09. Empty27th April 2009, 14:35 by mbdcl

» Unit No.5 : Status of Pending BOP work.
Status Report of Unit No.6 Construction as on 12.03.09. Empty27th April 2009, 14:15 by mbdcl

» Unit No.5 : Status of Pending BOP work.
Status Report of Unit No.6 Construction as on 12.03.09. Empty27th April 2009, 14:14 by mbdcl

» Updated Status of Balance work on Main Plant package
Status Report of Unit No.6 Construction as on 12.03.09. Empty13th March 2009, 18:00 by mbdcl

» Updated Status of Unit-5 Balance Work for BOP Package
Status Report of Unit No.6 Construction as on 12.03.09. Empty12th March 2009, 19:12 by mbdcl

» Status Report of Unit No.6 Construction as on 12.03.09.
Status Report of Unit No.6 Construction as on 12.03.09. Empty12th March 2009, 14:48 by mbdcl

» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
Status Report of Unit No.6 Construction as on 12.03.09. Empty9th February 2009, 18:03 by mbdcl


    Status Report of Unit No.6 Construction as on 12.03.09.

    avatar
    mbdcl


    Posts : 9
    Join date : 2009-02-04

    Status Report of Unit No.6 Construction as on 12.03.09. Empty Status Report of Unit No.6 Construction as on 12.03.09.

    Post  mbdcl 12th March 2009, 14:48

    1. Date of Order : 23.03.07

    2. Time of commercial operation: 33 months

    3. Progress of Work:

    A. Boiler Foundations : Complete

    B. Auxiliaries : ID Fan- A foundation complete.

    ID Fan - B foundation incomplete.

    PA & FD Fan foundations not started to facilitate Boiler erection.

    C. Boiler Erection:

    i) Non-pressure Parts : 1973 MT achieved (scope-3920 MT)

    ii) Pressure Parts : 746 MT achieved (scope-2593 MT)

    (In Details : LTSH Coils erection is in progress in Back Pass. 36 coils erected out of 72. *Boiler Erection in Front pass is suffering following non-availability of Roof & Sequential Structural items).

    D. ESP : 1st tier Erection of Columns/Tie Bracings complete in C & D pass.

    2nd tier erection is in progress in C & D pass.

    (Total achieved 397MT out of 4072 MT).

    E. Power House

    i) Civil work : All Main Column foundations complete.

    CW Pit & CEP foundations complete.

    3no BFP foundations & Oil Cooler Pits complete.

    TG Foundation completed on 22.02.09.

    Operating Floors : Only two panels cast (one at +8.5M & another at +13.5M). Suffering for Manpower crisis (Skilled).

    ii) Structural work : Scope-4500 MT. Released – 4500MT. Fabrication Achieved- 3758MT. Erected - 2553MT.

    (In details : 34no Columns are erected out of 40no, 7no Roof Truss erected in TG Hall portion out of 10no, 12no Crane Girders erected out of 20no and erection of Floor Beams is in slow progress at various level).


    F. ESP Control Room : Floor at EL+4.0M cast. Floor at +9.0M and +13M partly cast. Brickwork also taken up. (Manpower Crisis).

    G. Chimney : Shell casting achieved till EL+ 204.7M.

    H. Cooling Tower : Basin Floor raft cast for nine (9) Cells (total 13no). Wall/Columns/Tie Beams casting in progress for 2nd/3rd level.

    I. CW Pump house : i) CW Sump portion : Base Raft cast. (Suffering for Shortage of Skilled Manpower).

    ii) Feed Pool : Foundations of both side Walls cast. (Suffering for Shortage of Skilled Manpower).

    iii) CW Duct :Total 217RM of Base Raft cast out of 247RM. Wall & Top Cover Slab casting in very
    slow progress.


    J. Clf Wat Reservoirs & PH : Excavation completed. Reinforcement work for Bottom Base raft taken up for 40% area in progress. (Shortage of Skilled Manpower).

    K. Mill Bunker : Excavation done for 50% area as front cleared.

    8no Column Foundations complete and 2no in progress. Reinforcement work for Mill-D, E, F Foundations in progres.

    Fabrication in progress for 3no Columns (total 20no).

    Fabrication achieved 75 MT out of 4000MT.

    (Resource crisis). (Very Critical).


    L. CW Pipe Laying : Excavation started.

    M. Transformer Yard : Excavation started for GT on 12.03.09.

    N. 220kV Switchyard : Work front available for 60% area. Excavation started for Tower Foundations.

    O. Ash Handling System : Order Placed on M/s. DCIPS. Contractor not mobilized yet. Drawings are not available.
    Time of completion–22 months. (Very Critical).

    P. Erection of TG & Aux : Vendor Ordering expected to be completed by 1st week of April’09.

      Current date/time is 27th April 2024, 12:17