Santaldih Thermal Power Station - WBPDCL

Would you like to react to this message? Create an account in a few clicks or log in to continue.
Santaldih Thermal Power Station - WBPDCL

This site is made for sharing information of STPS & on going projects at STPS - Unit#5 and Unit#6

Latest topics

» santhaldih tps web site
Updated Status of Balance work on Main Plant package Empty25th June 2013, 13:34 by rajena

» Progress Report of Unit No. 6 for the month of May 2009
Updated Status of Balance work on Main Plant package Empty19th June 2009, 14:15 by mbdcl

» Progress/Program of M/s. BHEL for Major Balance Activities.
Updated Status of Balance work on Main Plant package Empty27th April 2009, 14:35 by mbdcl

» Unit No.5 : Status of Pending BOP work.
Updated Status of Balance work on Main Plant package Empty27th April 2009, 14:15 by mbdcl

» Unit No.5 : Status of Pending BOP work.
Updated Status of Balance work on Main Plant package Empty27th April 2009, 14:14 by mbdcl

» Updated Status of Balance work on Main Plant package
Updated Status of Balance work on Main Plant package Empty13th March 2009, 18:00 by mbdcl

» Updated Status of Unit-5 Balance Work for BOP Package
Updated Status of Balance work on Main Plant package Empty12th March 2009, 19:12 by mbdcl

» Status Report of Unit No.6 Construction as on 12.03.09.
Updated Status of Balance work on Main Plant package Empty12th March 2009, 14:48 by mbdcl

» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
Updated Status of Balance work on Main Plant package Empty9th February 2009, 18:03 by mbdcl


    Updated Status of Balance work on Main Plant package

    avatar
    mbdcl


    Posts : 9
    Join date : 2009-02-04

    Updated Status of Balance work on Main Plant package Empty Updated Status of Balance work on Main Plant package

    Post  mbdcl 13th March 2009, 18:00

    Fixing Balance Door & Windows and all Rolling Shutters
    Sl No

    [/center]Description[/center]
    Cumulative Progress

    Virtually no progress in this month
    A

    Power House Building
    1

    Brickwork/Facia/plaster balance on A row EL 0.M to EL 13.5/8.5M

    Above 13.5M, major work completed. 0.0M to 8.5M is in slow progress for manpower crisis.
    2

    AHU rooms (pending work)
    AHU Rooms (on A-row) Finishing work in progress.
    AHU Room in B-C bay/ 19.5M no action.
    3

    DG Room

    4

    SWAS Room : False Ceiling & AC for Dry Room etc.

    5



    6

    7



    8



    9



    10