Sl No | [/center]Description[/center] | Cumulative Progress |
Virtually no progress in this month A | Power House Building | |
1 | Brickwork/Facia/plaster balance on A row EL 0.M to EL 13.5/8.5M | Above 13.5M, major work completed. 0.0M to 8.5M is in slow progress for manpower crisis. |
2 | AHU rooms (pending work) | AHU Rooms (on A-row) Finishing work in progress. AHU Room in B-C bay/ 19.5M no action. |
3 | DG Room | |
4 | SWAS Room : False Ceiling & AC for Dry Room etc. | |
5 | | |
6 | ||
7 | | |
8 | | |
9 | | |
10 | ||
Search
Latest topics
Updated Status of Balance work on Main Plant package
mbdcl- Posts : 9
Join date : 2009-02-04
|
|
25th June 2013, 13:34 by rajena
» Progress Report of Unit No. 6 for the month of May 2009
19th June 2009, 14:15 by mbdcl
» Progress/Program of M/s. BHEL for Major Balance Activities.
27th April 2009, 14:35 by mbdcl
» Unit No.5 : Status of Pending BOP work.
27th April 2009, 14:15 by mbdcl
» Unit No.5 : Status of Pending BOP work.
27th April 2009, 14:14 by mbdcl
» Updated Status of Balance work on Main Plant package
13th March 2009, 18:00 by mbdcl
» Updated Status of Unit-5 Balance Work for BOP Package
12th March 2009, 19:12 by mbdcl
» Status Report of Unit No.6 Construction as on 12.03.09.
12th March 2009, 14:48 by mbdcl
» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
9th February 2009, 18:03 by mbdcl